Material Planning for Upper Structure Work Based on the Material Requirement Planning (MRP) Method in the Kasih Ibu Hospital Construction Project, Surakarta

Authors

  • Aprilia Regita Tri Cahyani Universitas Pembangunan Nasional “Veteran” Jawa Timur
  • I Nyoman Dita Pahang Putra Universitas Pembangunan Nasional “Veteran” Jawa Timur

DOI:

https://doi.org/10.55927/fjmr.v3i5.9525

Keywords:

Economic Part Period, Least Unit Cost, Material Requirement Planning, Planning

Abstract

Material inventory in construction projects is something that needs to be managed because it affects the smooth running of a construction project. To overcome this problem, material scheduling was carried out based on the Material Requirement Planning (MRP) method using the Economic Part Period (EPP) lot size technique and the Least Unit Cost (LUC) lot size technique. This research aims to produce material planning processes and results. MRP is a scheduling method to find out the material and quantity of material needed, as well as when the order will be placed. The calculation results obtained using the MRP method are that the EPP lot size requires a total material inventory cost of IDR 20,847,682,834, while the LUC lot size requires an inventory cost of IDR 20,851,272,531. The difference in total costs is IDR 3,589,697 so the EPP lot size is more economical compared to LUC.

Downloads

Download data is not yet available.

References

Amdes, M. P., Puspita, F. M., & Yuliza, E. (2019). Penerapan metode Economic Part Period (EPP) dan metode Part Period Balancing (PPB) dalam perencanaan pengendalian persediaan alat suntik pada perusahaan farmasi. Jurnal Penelitian Sains, 21(3), 168-174. doi:https://doi.org/10.56064/jps.v21i3.522

Bayudhana, Z. D., & Kamandang, Z. R. (2023). Material Requirement Planning Berdasarkan Hasil Resource Leveling Pada Proyek Konstruksi Jalan Tol. Jurnal Peradaban Sains, Rekayasa dan Teknologi, 11(1), 259-271. doi:https://doi.org/10.37971/radial.v11i1.392

BSN. (2012). SNI 1726:2012 Tata Cara Perencanaan Gempa Untuk Struktur Bangunan Gedung dan Non Gedung. Jakarta: Badan Standardisasi Nasional Retrieved fromhttps://iisee.kenken.go.jp/worldlist/27_Indonesia/Indonesia_SNI_1726_2012_GEMPA.pdf

Chandradevi, A., & Puspitasari, N. B. (2016). Penerapan Material Requirement Planning (MRP) dengan Mempertimbangkan Lot Sizing dalam Pengendalian Bahan Baku pada PT. Phapros, Tbk. Performa, 15(1), 10. doi:https://doi.org/10.20961/performa.15.1.13760

Dianto, Z. N., & Widati, E. (2023). Analisis Management Inventory Untuk Menghindari Death Stock Product di TB. Sinar Baru. Jurnal Ilmiah Akuntansi, Keuangan, dan Bisnis, 4(1), 50-72. doi:https://doi.org/10.36490/value.v4i1.631

Febrianti, M. S., & Marzuki, M. (2011). Perencanaan Persediaan Bahan Material Percetakan Dengan Metode MRP (Material Requirements Planning) Studi Kasus CV. Krakatau di Bandar Lampung. Explore: Jurnal Sistem Informasi dan Telematika, 2(2), 331298. doi:https://doi.org/10.36448/jsit.v2i2.341

Juniarti, D. A. T., & Luxviyanta, C. A. (2021). Metode Pengendalian Persediaan dengan MRP (W. Kurniawan Ed.). Banyumas: CV. Pena Persada.

Khan, N. A., & Sitania, F. D. (2023). Analisis Perbandingan Metode Least Unit Cost, Silver Meal, dan Metode Perusahaan dalam Pengendalian Persediaan Plafon PVC (Studi Kasus: XYZ). G-Tech : Jurnal Teknologi Terapan, 7(1), 155-164. doi:https://doi.org/10.33379/gtech.v7i1.1890

Lienardo, D. A., & Jin, O. F. (2020). Analisis Perbandingan Metode Material Requirements Planning (MRP) Dengan Metode Pengendalian Material Di Proyek A. JMTS: Jurnal Mitra Teknik Sipil, 3, 223-236. doi:https://doi.org/10.24912/jmts.v3i2.7045

Maddeppungeng, A., Desdiani, D., & Aditya, R. A. (2019). Analisis Risiko Biaya Dan Waktu pada Pelaksanaan Pekerjaan Struktur Atas Proyek Gedung Bertingkat Tinggi (Studi Kasus: Proyek Bangunan Gedung Bertingkat Tinggi di DKI Jakarta dan Sekitarnya). Fondasi: Jurnal Teknik Sipil, 8(2), 109-119. doi:http://dx.doi.org/10.36055/jft.v8i2.7347

Maddeppungeng, A., Setiawati, D. N., & Tuqa, B. (2021). Perencanaan Persediaan Material Dengan Menggunakan Metode Material Requirement Planning (MRP) Pada Proyek Apartemen (Studi Kasus: Proyek Pembangunan Nines Plaza & Residence Tower B). Fondation: Journal of Civil Engineering, 10(1), 69-80. doi:https://doi.org/10.36055/fondasi.v10i1.10624

Messah, Y. A., Widodo, T., & Adoe, M. L. (2013). Kajian Penyebab Keterlambatan Pelaksanaan Proyek Konstuksi Gedung Di Kota Kupang. Jurnal Teknik Sipil, 2(2), 157-168. doi:https://doi.org/10.35508/jts.2.2.157-168

Nursyanti, Y. (2019). Persediaan Kebutuhan Bahan Baku Komponen Produk Rumah Lampu Downlight (Rd). Jurnal Manajemen, 9(1), 300195. doi:https://doi.org/10.26460/jm.v9i1.991

Setiya, T., Raharjo, T., & Hadiwibowo, Y. (2022). Manajemen Pembangunan Berkelanjutan Desa (SDGs Desa) Dimulai dari Penyusunan Peraturan Desa SDGs Desa. CONSEN: Indonesian Journal of Community Services Engagement, 2(2), 54-66. doi:http://dx.doi.org/10.57152/consen.v2i2.457

Sungkono, M. A., & Sulistiyowati, W. (2016). Perencanaan dan Pengendalian Bahan Baku Untuk Meningkatkan Efisiensi Produksi Dengan Metode Material Requirement Planning dan Analytical Hierarchy Process di PT. XYZ. Spektrum Industri, 14(1), 11. doi:http://dx.doi.org/10.12928/si.v14i1.3684

Yasa, I. M. S., & Mandala, K. (2020). Material Requirement Planning Untuk Memenuhi Produksi Pada CV. Bangun Cipta Artha Di Badung. E-Journal Manajemen, 9. doi:https://doi.org/10.24843/EJMUNUD.2020.v09.i02

Downloads

Published

2024-05-30

How to Cite

Aprilia Regita Tri Cahyani, & I Nyoman Dita Pahang Putra. (2024). Material Planning for Upper Structure Work Based on the Material Requirement Planning (MRP) Method in the Kasih Ibu Hospital Construction Project, Surakarta. Formosa Journal of Multidisciplinary Research, 3(5), 1467–1480. https://doi.org/10.55927/fjmr.v3i5.9525

Issue

Section

Articles