Feasibility Analysis of Regular Gas Station Development Projects in Relation to the Economy

Authors

  • Trisna Ferdy Rediansyah Universitas Swadaya Gunung Jati Cirebon
  • Agung Ari Andono Universitas Swadaya Gunung Jati Cirebon
  • Ohan Farhan Universitas Swadaya Gunung Jati Cirebon
  • Saihul Anwar Universitas Swadaya Gunung Jati Cirebon

DOI:

https://doi.org/10.55927/ijar.v4i11.15736

Keywords:

Petrol Stations, Project Feasibility, NPV, Payback Period, BCR

Abstract

This study analyzes the feasibility of the construction of regular petrol stations in Sepaku District, North Penajam Paser Regency, East Kalimantan. The need for development arises due to the increase in the number of vehicles that is not proportional to the availability of fuel infrastructure. A quantitative approach is used through fuel demand analysis, RAB preparation, and economic evaluation with NPV, BCR, and Payback Period. The results show that Semoi Dua Village is strategic because it is on the path to IKN with high population growth. Fuel needs are estimated at ±311,000 liters per week. The project is economically feasible with a positive NPV of IDR 15 billion, a BCR of 1.3, and a payback period of four years. Petrol stations are considered prospective operationally and economically.

Downloads

Download data is not yet available.

References

Hidayat, A., & Santosa, E. (2021). Studi Kelayakan Pembangunan SPBU di Wilayah Perbatasan Indonesia. Jurnal Pembangunan Ekonomi, 9(1).

Wahyudi, S., & Siti, A. (2022). Analisis Pengaruh Fluktuasi Harga BBM terhadap Pendapatan SPBU. Jurnal Ekonomi dan Bisnis, 11(5).

Badan Pusat Statistik Kota Samarinda. (2025). Jumlah Penduduk Menurut Kabupaten/Kota di Provinsi Kalimantan Timur (Ribu), 2025.

Badan Pusat Statistik Provinsi Kalimantan Timur. (2024). Jumlah Kendaraan Bermotor Menurut Kabupaten/Kota dan Jenis Kendaraan di Provinsi Kalimantan Timur (unit).

Bakti, H., Setiawan, B. I. & Suroto, W. M. (2021). “Analisis Kelayakan Investasi SPBU Mikrosite Indomobil di Desa Grajagan”. Jurnal Sebatik 25(2).

Abimanyu, A., Mudjanarko, S., & Moetriono, H. (2022). “Analisis Investasi Pada Proyek Pembangunan Jalan Tol Pasuruan-Probolinggo”. Jurnal Spesialis Teknik Sipil, 3(2).

Nugraha, O. D. W., Taufiq, M., Apriliano, D. D., Khamid, A., & Wahidin. (2023). “Analisis Kelayakan Investasi Proyek Pembangunan Perumahan di Tinjau dari Aspek Teknis dan Finansial”. Jurnal Penelitian Sains, Keteknikan dan Informatika, 1(3).

Sukarjo, D. H., Putra. F. P., & Widyatami. F. S. (2024). “Analisis Kelayakan Investasi Pada Proyek Perumahan Mahardika Residence Sesuai Analisis Biaya Dan Analisis Permintaan”. Seminar Nasional Rekayasa, Sains dan Teknologi, 2(1).

[ITB thesis / kajian 2022 Forecasting demand for fuel energy and comparative assessments — metodologi peramalan permintaan BBM (time-series & proyeksi).

Zhu, J., et al. (2024). Multi-Objective Optimization of Urban Gas Station Site Selection — MDPI.

My Pertamina. (2025). SPBU My Pertamina.

Keputusan Direktur Jendral Minyak dan Gas Bumi. (2023). Keputusan Direktur Jendral Minyak dan Gas Bumi Nomor 409.K/MG.06/DJM/2023 tentang Pedoman Teknis Keselamatan Peralatan dan Instalasi Serta Pengoperasian Instalasi Stasiun Pengisian Bahan Bakar Minyak Untuk Masyarakat Umum. Jakarta: Kementrian Energi dan Sumber Daya Mineral

Ditjen Migas ESDM. (2024). Data Agen Penyalur BBM Pertamina Patra Niaga.

Published

2025-11-30

How to Cite

Rediansyah, T. F., Andono, A. A. ., Farhan, O. ., & Anwar, S. . (2025). Feasibility Analysis of Regular Gas Station Development Projects in Relation to the Economy. Indonesian Journal of Advanced Research, 4(11), 2499–2508. https://doi.org/10.55927/ijar.v4i11.15736