Time Analysis on the Kuningan Eastern Ring Road

Authors

  • Sigit Widiyatmo Prasetyo Universitas Swadaya Gunung Jati
  • Dicky Darmawan Universitas Swadaya Gunung Jati
  • Dinda Firdaus Universitas Swadaya Gunung Jati
  • Aryati Indah Kusumastuti Universitas Swadaya Gunung Jati

DOI:

https://doi.org/10.55927/ijar.v4i12.15876

Keywords:

Project Evaluation and Review Technique, Critical Path Method, Project Management, Time Management

Abstract

This analysis aims to identify delay factors and reduce the risk of delay in construction projects using the CPM method in the construction project of the East Ring Road Kuningan. The results of the study show that common factors that can have an impact on delays include the provision of materials, workforce readiness, and schedule adjustment to weather conditions. Therefore, supervision and control on critical routes must be carried out intensively to ensure that the project can be completed on time according to plan because delays in one activity alone will have a direct impact on the overall project completion.

Downloads

Download data is not yet available.

References

Indra Wati, Nurmiati Z & Nur Adyla S, 2018. Analisis Penerapan Manajemen Waktu Pada Proyek Jalan Kabupaten Polewali Mandar

Mochamad Choerul Anam & Ronny Durrotun Nasihien, 2019. Analisis Faktor-Faktor yang Mempengaruhi Kinerja Sumber daya Manusia Menggunakan Metode Diskriptif dan Diskriminan pada Proyek Konstruksi di PT.X. Publikasi Riset Orientasi Teknik Sipil.

I Gusti Ngurah Wiryadharma Verdianata, Ni Komang Armaeni & Ni Made Widya Pratiwi, 2023 Perencanaan Pelaksanaan Proyek Konstruksi Pada Proyek Pembangunan Rumah Susun Sekolah Tinggi Agama Hindu Negeri Mpu Kuturan Singaraja. Jurnal Teknik Gradien

Ma’rifatul Muniroh, Meidy Kempa & C.G. Buyang, 2021. Pengendalian Biaya dan Waktu Dengan Earned Value Concept Pada Proyek Penataan Bangunan. Jurnal Simetrik (Sipil, Mesin, Listrik)

Alfin Ali Kadzafi,Moch.Khamim dan Marjono, 2021. Penyusunan Project Planning Pembangunan Jalan Tol Balikpapan -Samarinda Seksi 2.2. Jurnal Online Skripsi Manajemen Rekayasa Konstruksi (JOS-MRK)

Fahirah & Tlantan, 2022. Identifikasi Risiko Yang Mempengaruhi Pelaksanaan Proyek Konstruksi Jalan di Kota Palu Berdasarkan Persepsi Konsultan. Rekontruksi Tadulako,

Ganesstri Padma Arianie, Nia Budi Puspitasari, 2017. Perencanaan Manajemen Proyek Dalam Meningkatkan Efisiensi dan Efektifitas Sumber Daya Perusahaan (Studi Kasus : Qiscus Pte Ltd). J@ti Undip: Jurnal Teknik Industri,

Danang Hadicara, Abdul Rochim & Pratikso, 2023. Penggunaan Metode PERT dan CPM dalam Proyek Pembangunan Jalan. Jurnal Pondasi

Suwarni & Anondho, 2021. Perbandingan Perhitungan Volume Kolom Beton Antara Building Information Modeling Dengan Metode Konvensional. JUTEKS - JURNAL TEKNIK SIPIL,

Tiurma Elita Saragi, Nurvita Insani Simanjuntak & Aprilta Tarigan, 2023. Metode Pelaksanaan dan Pengendalian Mutu Perkerasan Lentur Pekerjaan Peningkatan Struktur Jalan Pada Ruas Jalan Sigalingging Huta Jungak Kabupaten Dairi. CONSTRUCT : Jurnal Teknik Sipil,

Asrola, Sofyan M. Saleh, dan Muhammad Isya, 2018. Karakterisik Campuran Aspal Beton AC-WC Dengan Substutisi Buton Rock Asphalt Terhadap Rendaman Air Berlumpur. Jurnal Arsip Rekayasa Sipil dan Perencanaan,

Yogi Oktopianto & Rukman, 2021. Analisis Degradasi Performa Marka Jalan Thermoplastik pada Jalan Tol. Jurnal Aplikasi Teknik Sipi,

Junaedi Manto, 2016. Mengidentifikasi Durasi Dan Tenaga Kerja Berdasarkan Analisa Harga Satuan Pekerjaan (AHSP) Pada Perencanaan Pekerjaan Perumahan Villa Idaman Boalemo. Jurnal Peradaban Sains Rekayasa dan Teknologi,

Mar’aini, Y Rahmat Akbar, 2022. Penentuan Jalur Kritis untuk Manajemen Proyek (Studi Kasus Pembangunan Jalan Selensen- Kota Baru- Bagan Jaya). Jurnal Pustaka Manajemen,

Published

2025-12-31

How to Cite

Prasetyo, S. W., Darmawan, D. ., Firdaus, D. ., & Kusumastuti, A. I. . (2025). Time Analysis on the Kuningan Eastern Ring Road. Indonesian Journal of Advanced Research, 4(12), 2673–2688. https://doi.org/10.55927/ijar.v4i12.15876